Why this couldn’t wait

Why this couldn’t wait

Gas was venting from the production casing, leaving a sheen on the water. The platform leaned 12 degrees, its deck resting on just two legs and its well conductors pushed 17 feet off vertical.

The call we made

The call we made

Righting the platform risked further damage, so we stabilized it in place, braced its legs, secured the failed connection, and restored access to critical valves. Make-safe and temporary abandonment took just eight days against a ten-day plan. 

serviceTopElement
Short-term containment meets long-term XX

Short-term containment meets long-term XX

Speed is usually where discipline slips. Every major risk here was mapped from drone footage, survey data, and well records before anyone boarded, and every barrier was set, tested, and logged. After the immediate danger was mitigated, we returned six months later to cut all four facings and lift them out as a 102-foot unit.

  • 2 days from sheen report to survey
  • 8 days to make safe and abandon, against a 10-day plan
  • 4 casings removed, 20 feet below the mudline

Anyone can have a good project.

Here's what makes it repeatable.

South_Pass@2x.e558b606
Ingredients for Project Excellence 

Explore how early diligence, risk assessment, and contingency design lay the groundwork for flawless delivery.

Legacy_Well@2x.004f02d2
Safety as the Through Line

Learn how safety at Promethean is built into procurement, planning, and execution.

Right_of_Way@2x.6339072b
AI Across the Asset Lifecycle

Discover how Promethean uses connected data and AI to improve evaluation, planning, operations, and decommissioning.

Have an asset in mind? 

Tell us what you're working with. We'll create a strategy that benefits your bottom line, ESG goals, and operations.

Dual Image-1