Why this couldn’t wait
Gas was venting from the production casing, leaving a sheen on the water. The platform leaned 12 degrees, its deck resting on just two legs and its well conductors pushed 17 feet off vertical.

The call we made
Righting the platform risked further damage, so we stabilized it in place, braced its legs, secured the failed connection, and restored access to critical valves. Make-safe and temporary abandonment took just eight days against a ten-day plan.


Short-term containment meets long-term XX
Speed is usually where discipline slips. Every major risk here was mapped from drone footage, survey data, and well records before anyone boarded, and every barrier was set, tested, and logged. After the immediate danger was mitigated, we returned six months later to cut all four facings and lift them out as a 102-foot unit.
- 2 days from sheen report to survey
- 8 days to make safe and abandon, against a 10-day plan
- 4 casings removed, 20 feet below the mudline
Anyone can have a good project.
Here's what makes it repeatable.

Ingredients for Project Excellence
Explore how early diligence, risk assessment, and contingency design lay the groundwork for flawless delivery.

Safety as the Through Line
Learn how safety at Promethean is built into procurement, planning, and execution.

AI Across the Asset Lifecycle
Discover how Promethean uses connected data and AI to improve evaluation, planning, operations, and decommissioning.
Have an asset in mind?
Tell us what you're working with. We'll create a strategy that benefits your bottom line, ESG goals, and operations.